Town of Rowe

Network Build Progress as of October 23, 2018

  • State Grant first 3 disbursements received
  • Pole survey complete and pole applications submitted.
  • Fiber design complete. https://autode.sk/2zCfp4N
  • New poles on Davis Mine Rd installed.
  • New conduit on Davenport Rd installed (thanks Tom Danek for job well done).
  • National Grid make-ready complete and licenses received. Verizon is working on make-ready.
  • Contract signed with Sertex to install fiber once make-ready is complete.
  • Equipment hut ordered and site prep underway.
  • Estimated to start service in March 2019.

Please check back for updates.

Drop (Installation) Policy and Surcharge

We will have a pre-signup period up until construction is complete. Exact dates will be announced. We anticipate that anyone who signs up prior to the deadline will receive free ‘standard’ installation. A ‘standard’ installation is one that does not require replacing poles or installing new poles or conduit. In those cases we may have to charge at least part of the cost of new poles and/or conduit, depending on budget considerations. If it is necessary, you will be informed of the charge and given an opportunity to continue with installation or not be charged. Note that there is a separate one-time $99 activation fee for starting up service that is separate than physical installation.

We do not plan to add any surcharge to the WiredWest prices for service. Debt service and depreciation reserve costs will be paid out of tax revenue. If we receive excess revenue at the end of any year, we will apply those to offset the depreciation reserve contributions.

Pre-signup

Please check back for updates.